Skip to content

Language

Colour scheme

Construction management in depth

Scheduling in depth

How a robust schedule comes about: activities and dependencies, durations from the building model and control during construction, using a shell construction as the example.

1Scheduling

We structure the project into activities, link them through technological and organisational dependencies and determine the critical path. The result is a schedule that makes sequence, durations and float transparent, from the master schedule for project development to the detailed schedule for the site.

Site overheads (standby)
Site setup3 activities
BE aufbauen25/02/26 - 05/03/26
TDK aufstellen05/03/26 - 11/03/26
Vermessung Absteckung11/03/26 - 13/03/26
Earthworks5 activities
Oberbodenabtrag13/03/26 - 16/03/26
Baugrubenaushub16/03/26 - 19/03/26
Böschungsherstellung19/03/26 - 23/03/26
Planum + Kiesschüttung23/03/26 - 25/03/26
Wasserhaltung16/03/26 - 06/04/26
Foundation / base slab7 activities
Magerbeton25/03/26 - 26/03/26
Randschalung BP26/03/26 - 30/03/26
PE-Folie / Abdichtung30/03/26 - 31/03/26
Bewehrung Bodenplatte31/03/26 - 10/04/26
Beton Bodenplatte10/04/26 - 14/04/26
BP Nachbehandlung + Ausschalen Randschal.14/04/26 - 16/04/26
Bodenrückverfüllung16/04/26 - 20/04/26
Ground floor8 activities
Wände EG: Schalen20/04/26 - 19/05/26
Wände EG: Bewehren19/05/26 - 28/05/26
Wände EG: Betonieren28/05/26 - 29/05/26
Wände EG: Ausschalen29/05/26 - 03/06/26
Decke EG: Einschalen03/06/26 - 09/06/26
Decke EG: Bewehren09/06/26 - 16/06/26
Decke EG: Betonieren16/06/26 - 17/06/26
Decke EG: Nachbehandlung/Teilausschalen17/06/26 - 26/06/26
1st floor8 activities
Wände 1.OG: Schalen26/06/26 - 03/07/26
Wände 1.OG: Bewehren03/07/26 - 09/07/26
Wände 1.OG: Betonieren09/07/26 - 10/07/26
Wände 1.OG: Ausschalen10/07/26 - 14/07/26
Decke 1.OG: Einschalen14/07/26 - 20/07/26
Decke 1.OG: Bewehren20/07/26 - 30/07/26
Decke 1.OG: Betonieren30/07/26 - 06/08/26
Decke 1.OG: Nachbehandlung06/08/26 - 17/08/26
2nd floor8 activities
Wände 2.OG: Schalen17/08/26 - 07/09/26
Wände 2.OG: Bewehren07/09/26 - 21/09/26
Wände 2.OG: Betonieren21/09/26 - 28/09/26
Wände 2.OG: Ausschalen28/09/26 - 06/10/26
Decke 2.OG: Einschalen06/10/26 - 27/10/26
Decke 2.OG: Bewehren27/10/26 - 06/11/26
Decke 2.OG: Betonieren06/11/26 - 13/11/26
Decke 2.OG: Nachbehandlung13/11/26 - 24/11/26
3rd floor8 activities
Wände 3.OG: Schalen24/11/26 - 15/12/26
Wände 3.OG: Bewehren15/12/26 - 29/12/26
Wände 3.OG: Betonieren29/12/26 - 05/01/27
Wände 3.OG: Ausschalen05/01/27 - 13/01/27
Decke 3.OG: Einschalen13/01/27 - 03/02/27
Decke 3.OG: Bewehren03/02/27 - 15/02/27
Decke 3.OG: Betonieren15/02/27 - 22/02/27
Decke 3.OG: Nachbehandlung22/02/27 - 03/03/27
4th floor8 activities
Wände 4.OG: Schalen03/03/27 - 24/03/27
Wände 4.OG: Bewehren24/03/27 - 07/04/27
Wände 4.OG: Betonieren07/04/27 - 14/04/27
Wände 4.OG: Ausschalen14/04/27 - 22/04/27
Decke 4.OG: Einschalen22/04/27 - 13/05/27
Decke 4.OG: Bewehren13/05/27 - 25/05/27
Decke 4.OG: Betonieren25/05/27 - 01/06/27
Decke 4.OG: Nachbehandlung01/06/27 - 10/06/27
5th floor8 activities
Wände 5.OG: Schalen10/06/27 - 01/07/27
Wände 5.OG: Bewehren01/07/27 - 15/07/27
Wände 5.OG: Betonieren15/07/27 - 22/07/27
Wände 5.OG: Ausschalen22/07/27 - 30/07/27
Decke 5.OG: Einschalen30/07/27 - 20/08/27
Decke 5.OG: Bewehren20/08/27 - 01/09/27
Decke 5.OG: Betonieren01/09/27 - 08/09/27
Decke 5.OG: Nachbehandlung08/09/27 - 17/09/27
Stairs and landings6 activities
Treppenläufe: Schalen17/09/27 - 24/09/27
Treppenläufe: Bewehren24/09/27 - 27/09/27
Treppenläufe: Betonieren27/09/27 - 29/09/27
Treppenpodeste: Schalen29/09/27 - 01/10/27
Treppenpodeste: Bewehren01/10/27 - 04/10/27
Treppenpodeste: Betonieren04/10/27 - 07/10/27
Lift shafts (2)3 activities
Aufzugsschächte: Kletterschalung20/04/26 - 30/04/26
Aufzugsschächte: Bewehren30/04/26 - 06/05/26
Aufzugsschächte: Betonieren06/05/26 - 11/05/26
Shell completion3 activities
Rohbau-Reinigung und Entsorgung Bauschutt07/10/27 - 11/10/27
TDK abbauen11/10/27 - 14/10/27
BE abbauen14/10/27 - 19/10/27
critical path with float standby period (overheads)Expand a group to see its individual activities (original German names). On narrow screens, swipe sideways.
Fig. 1 Schedule of a shell construction in activity groups with the critical path highlighted. The groups can be expanded.Source: rheonda, example project

2Model-based foundations

Robust durations start with quantities. We read them from the building model, price them with productivity rates from the estimate and derive durations and resource demand.

The model’s element structure (foundation, walls, columns, slabs) is also the bridge to 4D simulation: the same model that supplies the quantities later visualises the construction sequence.

3D shell model with slabs, walls and columns
Fig. 2 Element geometry of a shell construction read from the IFC model.Source: rheonda

3Schedule control during construction

  1. Plan-actual comparison

    Record progress regularly and compare it with the schedule.
  2. Updating

    Adapt the schedule to the actual course and show the effect on completion.
  3. Countermeasures

    Develop measures to secure the schedule and assess them for cost and quality.
  4. Reporting

    Present the schedule status clearly for clients, project management and subcontractors.
Our serviceConstruction schedulingWe create, review and control schedules, derived from estimate and building model and aligned with cost and quality targets.